The County's New Administrative Home
Lac Ste. Anne County Council acknowledged the need to build a new administration office. Since that time, Council and staff have been touring other municipal offices to learn what's worked and what hasn't. They listened to suggestions during those tours, hired experts to help guide the process, manage the project, and develop a design that meets the County's growing needs.On September 15, 2015, Council approved funding for the new administration building. Approximately 80% of funding will come from grants. The balance is from money already saved for this project. The estimated construction cost of the building is $8.3 million. The total estimated project cost is $11.7 million.
Project Status Updates May 26, 2017
The project is still working towards a completion of May 31, 2017. However, it was decided that the substantial completion and the final completion inspections will not be done until the floor issue has been resolved. All parties involved are currently working on fixing the issue which may cause some delays on handover. Casman is now setting up commissioning, testing and inspections. With regards to the finishing Casman is working on wrapping up final touches and should be completing all the work toward the end of May. The expected move-in date is mid to late June.Construction Status
Casman has confirmed that they are aiming to have all the work completed by May 31, 2017All major construction materials are on site
Interior wall framing is complete
Drywall installation complete
Mudding and taping is nearly complete (approx. 98%)
Painting work is nearly complete including the vault (95%)
Millwork has been substantially installed (approx. 98%)
Majority of Flooring has been installed i.e. carpet, tiles and polished concrete (approx.98%)
Acoustic ceilings grids and tiles are nearly complete (95%)
Window and Glass installation is nearly complete (98%)
HVAC and the Mechanical equipment is in place (95%)
Testing/commissioning/balancing to start week of May 15th
Electrical work is in progress – Delayed due to disagreement between Casman and Electrical sub – Light fixtures are currently installed except bee hive lights which have arrived onsite (approx. 80%)
County’s contractors for the new Fire Protection system near complete (approx. 96%)
County to coordinate AV equipment and installation for the Council Chambers
Backup Generator installed. Connection to the building pending
Tie-in for the Fire protection system to be determined (extra design work)
Pending Decisions/Issues
Uneven Floors:
There are numerous offices where the flooring is uneven. The concrete floor either slopes down towards the exterior of the building or has a hump in the middle of the room.
Further investigation revealed that there is water under the slab which has caused the high plastic clay to heave. There are two likely reasons for the water, the site grading not completed or maintained properly in some areas causing the water to flow toward the foundation, or the downspouts are not discharging water further away from the building as should have been designed and constructed based on the geotechnical report.
Based on the geotechnical report, the site grading was to slope away from the building which was not the case as observed in some areas and the downspouts were to be at least 3m away from the building which is not how it has been designed.
Colliers Project Leaders provided recommendations (May 12) to possibly prevent further water infiltration and relieve the pressure from under the slab.
However, it is recommended that cores will be required to determine how much further the sub-grade will settle before repairing the floors.
County to confirm if they want to proceed with coring.
Fire Protection System:
County is currently working with own contractors to have this scope delivered prior to project completion as it is a critical component of occupancy.The county has made good progress on this work and is nearly complete.
The tie-in design was not in A&E’s scope and have requested additional fees, however a breakdown has been requested for the fee proposal.
Furniture:
The County will procure furniture. The County will coordinate delivery with Casman, once substantial completion is obtained. All the power requirements have been coordinated and Casman is proceeding with the changes.
A/V Systems:
County awarded the AV systems and will be coordinating the work.The County A/V company will work with Casman’s electrician to complete this. No further action required.
Schedule Delay:
Casman has now indicated a final completion/move-in date of May 31, 2017.
However, they are having a disagreement with the second electrical sub that was brought on board. Casman has brought onboard a third contractor and the work is ongoing.
Another Lien was filed by Ryfan (2nd contractor) in the amount of $172,000 which will be dealt with by Casman. Casman has indicated that they have a plan to take care of all Liens prior to building occupancy. An update to follow.
Budget
The project is currently on budget and the forecast is positive.
Total Project Budget: $11,729,663Total Committed Cost: $10,053,325
Original Construction Value: $7,953,604.81
Revised Construction Value: $8,507.009.58
Total Contingency Remaining: $739,639
Forecast Cost at Completion: $10,930,023
Approved Change Orders: $553,404.77
LSARA Lac Ste. Anne Ratepayers Association said...
ReplyDeleteThis Building was started as a "Priority Rush" and now they are trying to complete it as a "Priority Rush"!!!
Why would you "RUSH" to complete a Building when you have serious "Foundation Issues"?
This buildings 'Heaving Slab" is the buildings foundation and it should have been built to last the life expectancy of the building!
It is not a replaceable item!
The only reason to "Rush" the completion of this building is so the Contractor and the Project Manager get paid off and to turn over Possession of this mess to "YOU" the RATEPAYERS!!
For LSAC not to take this "ISSUE" seriously is ridiculous! The project manager says it's up to the County if they want to take "Core Samples". Excuse me! That should have been done Months ago when they first knew there was an Issue with the "HEAVING FLOORS"!!
Wake up people! Call your Councilor and demand that an unbiased Investigation gets done and put a halt on this mess until this "ISSUE" gets the attention it deserves!!!
Lac Ste. Anne County posted on May 30 "Lac Ste. Anne County wishes to clarify that there is zero impact to the Administration Building Budget from builders' liens." LSARA will be monitoring this Budget closely as these liens are not the only issues with the budget.
ReplyDeleteAlso in that post they have now recognized as LSARA had previously Posted " there are five Builder’s Liens, totaling approximately $395,000" NOT 1 Lien as LSAC stated in their "New Administrative Home Project Status Update May 26".