LSARA is a Not For Profit Association. We are all Ratepayers and Volunteers! The Ratepayers of Lac Ste. Anne County have made it clear that they want to be heard! LSARA is an important voice as we speak for a large number of people. 2500 people reading our blog posts in less than 24 hours tells us we are on the right track. IT'S A MATTER OF DOLLARS AND SENSE. 2023 Memberships are now available. $10 each or $20 per Family


Tuesday, May 30, 2017

Straight from the LSAC Web Site

Administration Office Information

The County's New Administrative Home

Lac Ste. Anne County Council acknowledged the need to build a new administration office. Since that time, Council and staff have been touring other municipal offices to learn what's worked and what hasn't. They listened to suggestions during those tours, hired experts to help guide the process, manage the project, and develop a design that meets the County's growing needs.

On September 15, 2015, Council approved funding for the new administration building. Approximately 80% of funding will come from grants. The balance is from money already saved for this project. The estimated construction cost of the building is $8.3 million. The total estimated project cost is $11.7 million.

Project Status Updates  May 26, 2017

The project is still working towards a completion of May 31, 2017. However, it was decided that the substantial completion and the final completion inspections will not be done until the floor issue has been resolved. All parties involved are currently working on fixing the issue which may cause some delays on handover. Casman is now setting up commissioning, testing and inspections. With regards to the finishing Casman is working on wrapping up final touches and should be completing all the work toward the end of May. The expected move-in date is mid to late June.

Construction Status

Casman has confirmed that they are aiming to have all the work completed by May 31, 2017 
WITH THE EXCEPTION OF THE UNEVEN CONCRETE FLOOR ISSUE! 

At this time the construction activity status is as follows:

All major construction materials are on site
Interior wall framing is complete
Drywall installation complete
Mudding and taping is nearly complete (approx. 98%)
Painting work is nearly complete including the vault (95%)
Millwork has been substantially installed (approx. 98%)
Majority of Flooring has been installed i.e. carpet, tiles and polished concrete (approx.98%)
Acoustic ceilings grids and tiles are nearly complete (95%)
Window and Glass installation is nearly complete (98%)
HVAC and the Mechanical equipment is in place (95%)
Testing/commissioning/balancing to start week of May 15th
Electrical work is in progress – Delayed due to disagreement between Casman and Electrical sub – Light fixtures are currently installed except bee hive lights which have arrived onsite (approx. 80%)
County’s contractors for the new Fire Protection system near complete (approx. 96%)
County to coordinate AV equipment and installation for the Council Chambers
Backup Generator installed. Connection to the building pending
Tie-in for the Fire protection system to be determined (extra design work)

Pending Decisions/Issues

Uneven Floors

There are numerous offices where the flooring is uneven. The concrete floor either slopes down towards the exterior of the building or has a hump in the middle of the room. 

Further investigation revealed that there is water under the slab which has caused the high plastic clay to heave. There are two likely reasons for the water, the site grading not completed or maintained properly in some areas causing the water to flow toward the foundation, or the downspouts are not discharging water further away from the building as should have been designed and constructed based on the geotechnical report. 

Based on the geotechnical report, the site grading was to slope away from the building which was not the case as observed in some areas and the downspouts were to be at least 3m away from the building which is not how it has been designed. 

Colliers Project Leaders provided recommendations (May 12) to possibly prevent further water infiltration and relieve the pressure from under the slab. 

However, it is recommended that cores will be required to determine how much further the sub-grade will settle before repairing the floors

County to confirm if they want to proceed with coring.

Fire Protection System: 

County is currently working with own contractors to have this scope delivered prior to project completion as it is a critical component of occupancy.The county has made good progress on this work and is nearly complete. 

The tie-in design was not in A&E’s scope and have requested additional fees, however a breakdown has been requested for the fee proposal.

Furniture: 

The County will procure furniture. The County will coordinate delivery with Casman, once substantial completion is obtained. All the power requirements have been coordinated and Casman is proceeding with the changes.

A/V Systems: 

County awarded the AV systems and will be coordinating the work.The County A/V company will work with Casman’s electrician to complete this. No further action required.

Schedule Delay: 

Casman has now indicated a final completion/move-in date of May 31, 2017. 

However, they are having a disagreement with the second electrical sub that was brought on board. Casman has brought onboard a third contractor and the work is ongoing. 

Another Lien was filed by Ryfan (2nd contractor) in the amount of $172,000 which will be dealt with by Casman. Casman has indicated that they have a plan to take care of all Liens prior to building occupancy. An update to follow.

Budget

The project is currently on budget and the forecast is positive.

Total Project Budget: $11,729,663
Total Committed Cost: $10,053,325

Original Construction Value: $7,953,604.81
Revised Construction Value: $8,507.009.58

Total Contingency Remaining: $739,639
Forecast Cost at Completion: $10,930,023

Approved Change Orders: $553,404.77

Risks

The following are the major risks that are being monitored at this time:

Schedule Delays: 

Overall the progress on site has been slow. 

The progress claims justify this slow progress in terms of completion of work per month. The percent completion of some of the items has been slower than what Casman had provided in the schedule. 

Mitigation: 

Work with the contractor and architect to resolve any issues in a timely manner and only pursue changes that will not affect the critical path of the schedule.

Design Coordination: 

Some of the responses from A&E have not been coordinated to include all sub consultant reviews and have caused confusion on site. 

At this time, it is important to provide clear responses and have resolution on any issues. 

Mitigation: 

The frequency of the Site Owners meetings has been increased, to ensure that the issues are being resolved and the work is progressing in order to meet the schedule. 

In addition, we are increasing the regular communication, and the timing of that communication, to help ensure all responses are clear to all parties involved, in a timely manner. Recent RFIs and queries have seen a same day response and this type of response time will be the plan until project completion.



2 comments:

  1. LSARA Lac Ste. Anne Ratepayers Association said...
    This Building was started as a "Priority Rush" and now they are trying to complete it as a "Priority Rush"!!!

    Why would you "RUSH" to complete a Building when you have serious "Foundation Issues"?

    This buildings 'Heaving Slab" is the buildings foundation and it should have been built to last the life expectancy of the building!
    It is not a replaceable item!

    The only reason to "Rush" the completion of this building is so the Contractor and the Project Manager get paid off and to turn over Possession of this mess to "YOU" the RATEPAYERS!!

    For LSAC not to take this "ISSUE" seriously is ridiculous! The project manager says it's up to the County if they want to take "Core Samples". Excuse me! That should have been done Months ago when they first knew there was an Issue with the "HEAVING FLOORS"!!

    Wake up people! Call your Councilor and demand that an unbiased Investigation gets done and put a halt on this mess until this "ISSUE" gets the attention it deserves!!!

    ReplyDelete
  2. Lac Ste. Anne County posted on May 30 "Lac Ste. Anne County wishes to clarify that there is zero impact to the Administration Building Budget from builders' liens." LSARA will be monitoring this Budget closely as these liens are not the only issues with the budget.

    Also in that post they have now recognized as LSARA had previously Posted " there are five Builder’s Liens, totaling approximately $395,000" NOT 1 Lien as LSAC stated in their "New Administrative Home Project Status Update May 26".

    ReplyDelete

Lac Ste. Anne Ratepayers Association Facebook

Please Join! We need your support.

Please Join! We need your support.

Please Inc.Ph#, Address, Legal Land Description, Division# of Each Member in the "Message" section.

Name

Email *

Message *

Payment for membership can be made via e-transfer to lsaracares@gmail.com

Payment for membership can be made via e-transfer to lsaracares@gmail.com

GET TO KNOW YOUR LSAC COUNCILLOR LET THEM KNOW HOW YOU FEEL

Joe Blakeman | Reeve, Councillor, Division 5

Email jblakeman@lsac.ca Ph. 780 918-1916


Lorne Olsvik | Councillor, Div. 1

Email lolsvik@lsac.ca Ph. 780 937-5360


Nick Gelych | Councillor, Div.2

Email ngelych@lsac.ca Ph. 780 9039393


George Vaughan | Councillor, Div. 3

Email gvaughan@lsac.ca Ph. 780 967-3469


Keven Lovich | Councillor, Div. 4

Email klovich@lsac.ca Ph. 780 785-8153


Ross Bohnet | Councillor, Div. 6

Email rbohnet@lsac.ca Ph. 780 786-4290


Lloyd Giebelhaus | Councillor, Div. 7

Email lgiebelhaus@lsac.ca Ph. 780 785-2095

WE WANT YOUR OPINIONS

ADD YOUR COMMENTS

RECENT COMMENTS ...... Please leave your comments on any of our posts. YOUR VALUED OPINION MATTERS!

CURRENT NEWS

LESS PROVINCIAL FUNDING FOR RURAL LAC STE. ANNE COUNTY How does this affect your LSAC Tax Bill?

WHAT THEY TOLD YOU THEN and WHAT THEY SAY NOW

IN CAMERA

FLUFF OR TRANSPARENCY

WHAT ARE THE COUNCILLORS DUTIES

WHAT ARE THE COUNCILLORS DUTIES
COUNCILLORS RESPONSIBILITIES

Alberta Government Municipal Affairs

View Our Current Top Priority Issues

LSARA. Powered by Blogger.

LSAC ORGANIZATIONAL CHART

LSAC ORGANIZATIONAL CHART
CLICK TO VIEW THE ORGANIZATIONAL CHART Welcome to the Lac Ste. Anne and Communities Ratepayers Association Web Site and Blog. The association will be a positive and credible advocate of Lac Ste. Anne County Communities. It will, by coordinated input, oversee that elected county officials are held to the terms and conditions of provincial laws and regulations. It will continuously strive to work for the betterment of all ratepayers. IT'S A MATTER OF DOLLARS AND SENSE.

THIS IS OUR COUNTY