This is a re-post of our original Post of March 26 2017 of our concerns that will finally be discussed in LSAC Council Chambers on April 13 2017. LSAC Updated their Administration Building Project Status Updates on their Web Site after our Post on Friday April 7 2017. The Update to the Building is Back Dated As March 15, 2017 and Reads as Follows:
Project Status Updates March 15, 2017
The contractor is currently working to complete the project such that the County can move-in by May, 2017. Based on the review, the progress on site has been gradual and some of the activities, especially the building envelope, are taking longer than expected. The project is on budget even with the potential delay costs.
Construction Status
Casman has confirmed that they are aiming to have the project substantially completed by February 8, 2017 and a final completion and County move-in date by end of May, 2017.
For More Information Visit:
http://lsac.ca/government/administration-office-information
Original Post March 26 2017 lsaracares.blogspot.ca
LSAC has had no updates This Year on their Web Site in regards to the Status of the Administration Building and the Costs to Date.
lsac.ca Administration Building Information
County office completion pushed back
By Joseph Quigley Mayerthorpe Freelancer
Tuesday, February 28, 2017 County office completion pushed back:
The completion date for construction of Lac Ste. Anne County's new administrative building is being pushed back two weeks to March 21.